Key facts
- Harvard University led a consortium of researchers in the study.1
- Virginia beat Oregon for its number of hyperscale data centers.1
- Oregon is home to the second-highest number of hyperscale data centers in the country.1
- Oregon’s hyperscale data centers contributed to 1.3 million metric tons of greenhouse gas pollution.1
Only Virginia, with 142 facilities, had more hyperscale data centers than Oregon, a recent Harvard University study found.1
The study’s findings were published Monday in the peer-reviewed journal Nature Sustainability.1
Oregon is home to the second-highest number of hyperscale data centers in the country
Researchers identified more than 400 total hyperscale facilities in the U.S. between May 2024 and April 2025, including 56 in Oregon.1
The researchers generally defined hyperscale facilities as housing several server-filled buildings of roughly 2,000 square meters each, with an average energy capacity of 40 MW.1
The study focused on hyperscale data centers because they are the largest, most powerful class of data centers designed to handle the largest computing and data storage loads.1
Analysts at the Lawrence Berkeley National Laboratory estimate hyperscale data centers will account for more than 90% of all data center electricity consumption by 2028.1
Energy demand and greenhouse gas pollution
Hyperscale data centers in Oregon, almost entirely in the eastern half of the state, required 11.1 terawatt-hours of energy to operate, equivalent to the amount of electricity that could power more than 1 million American homes for a year.1
Oregon’s hyperscale data centers contributed to 1.3 million metric tons of greenhouse gas pollution, equal to the pollution from more than 300,000 gas-powered cars in an average year, according to the study.1
The greenhouse gas pollution is less than that caused in Ohio or Iowa, which have fewer facilities but rely more on electricity powered by coal and natural gas.1
The study’s lead author, Gianluca Guidi, a postdoctoral fellow at Harvard University’s Department of Biostatistics, called the findings in a news release a “snapshot of a rapidly expanding industry.”1
Data center growth and regulation
Data center growth became a central issue in local and statewide political races during the last year, and several communities issued temporary moratoriums on new facilities.1
Oregon lawmakers and Gov. Tina Kotek are expected to propose new data center regulations during the 2027 legislative session that starts in January.1
Proposals could require more transparency around the facilities’ energy use, water consumption and on data centers’ access to property tax incentives meant to spur job growth in the state.1
Kotek in October mandated state agencies cease issuing environmental permits for new and expanded data center construction.1
Umatilla County in eastern Oregon, where the state’s largest concentration of large and hyperscale data centers are located, has sued.1
A September analysis from the consulting firm ECOnorthwest found that most of Umatilla County’s 22 data centers are hyperscale centers.1
Both the city of Umatilla and the county’s attorneys have asked a local judge to step in and overturn Kotek’s order pausing permitting.1